The problem: refusal or insufficient connection capacity
In many MV grid areas, available connection capacity is already exhausted. The investment then waits for a DSO grid upgrade, blocking the schedule and revenue.
How storage replaces a grid upgrade
The system operates in a power-limiting mode: grid draw never exceeds the contracted value, with the difference covered by the storage system. From the DSO's perspective, the site's load profile is flat and requires no new connection conditions.
Sizing parameters
| Power deficit | Peak duration | Capacity | Containers |
|---|---|---|---|
| 0.5 MW | 2 h | 1 MWh | 1 |
| 1 MW | 2 h | 2 MWh | 1 |
| 2 MW | 3 h | 6 MWh | 1–2 |
| 5 MW | 4 h | 20 MWh | 4 |