20 MWh Energy Storage — Grid-Scale Project for the Capacity Market

Short answer

A 20 MWh storage system is typically 10 MW / 20 MWh in a 2h configuration, made up of four 20ft containers at 5 MWh each, four PCS units at 2.5 MW each, and a 12.5 MVA transformer substation. This is the most common scale for projects entering capacity market auctions.

  • 4–8 × 20ft containers
  • 5–25 MW
  • 0.5C for the capacity market, 0.25C for ancillary services

Who this scale is for

  • A developer holding 10–25 MW grid connection terms
  • An owner of a solar or wind farm expanding the project into a hybrid
  • An entity entering a capacity market auction with a storage unit

Configuration, site and grid connection

Number of containers4–8 × 20ft containers
System power5–25 MW
C-rate0.5C for the capacity market, 0.25C for ancillary services
Land footprint0.4–0.8 ha including the on-site substation (GPZ)
Voltage levelMV 30 kV or HV 110 kV above 20 MW
Indicative CAPEXPLN 16–22 million for 10 MW / 20 MWh
Delivery schedule12–18 months including permitting and grid connection

Revenue models realistic for this scale

  • Capacity market agreement — standby revenue per MW of obligation
  • Ancillary services: aFRR, mFRR, primary frequency regulation
  • Arbitrage on the TGE power exchange and the balancing market

Reference implementation

ParameterValue
Configuration5–25 MW / 10–50 MWh
Containers4–8 × 20ft containers
Grid connectionMV 30 kV or HV 110 kV above 20 MW
Delivery time12–18 months including permitting and grid connection