When a building permit is required
Building law exempts storage systems up to 300 kWh from notification and permit requirements. All the industrial and utility-scale installations discussed on this site are above that threshold.
Spatial planning
If the site is covered by a local zoning plan (MPZP), we check whether technical infrastructure is permitted. Otherwise a zoning decision (WZ) is needed — realistically 4–8 months.
Environmental decision
Energy storage systems are generally not classified as projects that may significantly affect the environment, but for projects above 1 ha of built-up area, or when combined with a grid substation (GPZ), an environmental impact information sheet may be required.
| Stage | Duration |
|---|---|
| Zoning decision (WZ, if no MPZP) | 4–8 months |
| Building design and approvals | 2–3 months |
| Building permit | 65 statutory days |
| Connection conditions and agreement | in parallel, 6–12 months |