VoltGrid BESS1 MWh — 1000+ MWh

Key application · PV + BESS

Energy storage for solar farms — BESS from 1 MWh to 1000 MWh

Short answer

For a PV farm, the recommended ratio is 2 MWh of capacity per 1 MW of installed power, in a 4-hour configuration (0.25C). The storage system absorbs the surplus from the 11:00–15:00 window and releases it during the evening peak, at the same connection point.

  • No more selling during negative-price hours
  • Full use of the existing grid connection capacity
  • Retrofit of an existing farm without a new connection

Problem

A PV farm earns the least exactly when it produces the most

The solar production profile coincides with the hours of lowest market prices. The result is negative prices, curtailment and a capture price well below the average exchange price.

11:00–15:00

window in which most negative prices occur

5–12%

of annual production lost to curtailment

15–30%

gap between capture price and average exchange price

Negative prices in the 11:00–15:00 hours

When nationwide PV generation exceeds demand, the day-ahead market price drops below zero. An installation without storage then has two options: sell below zero or curtail production.

Curtailment — how much energy is lost each year

Generation-reduction orders and self-curtailment today take away 5–12% of a typical farm's annual volume. A 4-hour storage system captures most of that energy.

Capture price versus average exchange price

The capture price is the average price weighted by the actual production profile. For PV it is 15–30% lower than the average exchange price, because production is concentrated in the lowest-price hours. Storage shifts volume to higher-price hours and raises the capture price.

Sizing

Matching capacity to farm power

PV power → recommended capacity → C-rate → number of containers
PV farm powerBESS powerCapacityC-rate20 ft containers
1 MW0.5 MW2 MWh0.25C1
2 MW1 MW4 MWh0.25C1
5 MW2.5 MW10 MWh0.25C2
10 MW5 MW20 MWh0.25C4
20 MW10 MW40 MWh0.25C6–8
50 MW25 MW100 MWh0.25C16–20

Retrofitting an existing farm

Do the grid connection terms need to change

Yes — the installation becomes hybrid. If the power fed into the grid does not increase, the procedure comes down to amending the connection terms and the agreement, without building a new connection. Realistic timeframe: 90–150 days.

What about the PPA and the energy offtaker

Energy discharged from storage must be metered separately from energy covered by a PPA or a support scheme. In practice this means an additional metering configuration and an amendment to the sale agreement.

Space on the farm site

For 10 MWh, 150–300 m² is enough, including a service road and fire zone, usually near the existing transformer station.

Cost and payback period

Reference calculations
SystemCAPEXSimple payback
1 MW farm + 2 MWhPLN 1.9–2.6 million6–9 years
5 MW farm + 10 MWhPLN 8.8–12.0 million5–8 years
20 MW farm + 40 MWhPLN 32–44 million5–7 years

Scope of our delivery

  • Profitability analysis based on the farm's production data
  • Design, configuration selection and documentation for the connection-terms amendment
  • Liquid-cooled 20 ft containers, PCS, transformers, MV switchgear
  • EMS optimised for capture price and the balancing market
  • Commissioning, testing and O&M service with an LTSA

Lead magnet

Free profitability analysis for your farm

Give us four parameters — within 48 h we'll prepare a capacity recommendation, an estimate of captured energy and a CAPEX range.

This form is for industrial installations from 0.5 MW only. We do not serve residential installations.

FAQ

Request a quote — pricing in 48 h

Send us the project scale in MWh, the site location and the available grid capacity. We reply with a configuration, CAPEX range and delivery schedule.