VoltGrid BESS1 MWh — 1000+ MWh

Application · industry

Energy storage for a manufacturing plant — peak shaving and capacity charge reduction

Short answer

For a plant with a contracted capacity of 2–8 MW, a typical storage system is 1–5 MWh in a 2-hour configuration. Shaving 15–25% off the peak lowers the capacity charge and avoids exceeding contracted capacity without expanding the grid connection.

  • Capacity charge reduction during the 4 daily peak hours
  • No exceedance of contracted capacity and no overdraw penalties
  • Daily arbitrage on the B23 / B22 tariff

The problem: capacity charge and power peaks

A plant with 5 MW of contracted capacity and a 4-hour production peak pays a capacity charge calculated from consumption during peak hours. Limiting draw by 1.5 MW during those hours cuts the annual capacity charge by several hundred thousand PLN while also removing the risk of exceeding contracted capacity.

How BESS peak shaving works

The EMS measures consumption at the metering point and discharges the storage system whenever instantaneous power exceeds the set threshold. Charging takes place during the night trough or from surplus generation of an on-site PV installation. A 2 h (0.5C) configuration covers a typical single-shift peak profile.

Sizing parameters

Contracted capacity → recommended configuration
Contracted capacityBESS powerCapacity20 ft containers
1–2 MW0.5 MW1 MWh1
2–5 MW1 MW2 MWh1
5–8 MW2 MW4 MWh1–2
8–15 MW5 MW10 MWh2–3

Cost and payback

A 1 MW / 2 MWh block requires a capital outlay of PLN 1.9–2.6 million. Combining the effects of capacity charge reduction, arbitrage and avoided connection upgrades, the simple payback period is typically 5–8 years, shortening to 4–6 years with additional DSR participation.

Scope of delivery

  • Technical design, power and capacity sizing based on a 15-minute load profile
  • Liquid-cooled 20 ft container, PCS, transformer, MV switchgear
  • EMS integrated with the plant's higher-level control system (Modbus TCP / OPC UA)
  • Fire safety approvals, commissioning documentation, start-up and operator training
  • O&M service with a guaranteed 24-hour response time

FAQ

Request a quote — pricing in 48 h

Send us the project scale in MWh, the site location and the available grid capacity. We reply with a configuration, CAPEX range and delivery schedule.